Friday, 9 December 2011

The Turn of the Screw (not Britten)


It was with great excitement that, yesterday afternoon, we were able to witness the first turn of the screw.  Roger Hutton, of Potential Energy, proudly raised the main sluice gates and the turbine eased into action.  This was just a test of course, as the electricity board is still checking a few elements in the connection to the grid but we do expect to be contributing in a small, but nevertheless important, way to the sustainable output of the UK within a week.
All contracted plant is now off site as the civil work was completed on Monday, and it is now just testing, linking up the internet (so we can monitor performance) and work to get the telemetry settings right, all going on inside the 'shed of mystery' by the frightfully clever boffins who understand the wonders within.
So the heavy work is complete.  I will report once again when we begin the landscaping, fencing and aesthetic tidying work; but that will all have to wait until we are in a position to get machinery into the field, which would be impossible at present for the mud.

Sunday, 6 November 2011

Archimedes screw update - sluice gate arrives.

Last time I brought you up to speed to the point where the screw had arrived (all 8 tonnes of it), and we had successfully negotiated the 1 mile journey from the A36 down the hill across fields and along tracks, to its resting place in the ready-prepared concrete cradle:
Since then, the bearings have been connected up, and a shed built on top of the concrete platform in which the gear mechanism and control unit are housed.  This is seriously solid kit.
 The shed:
You might recall that there was a large tree root which needed to be removed from the mill leet wall before repairs to it could be made.  This was the result (it came out with quite a bit of wall attached - all of which will be reused in some project or other).
The enormous 360 excavator gave the remaining stones a hefty shove back into the hole created by the tree roots.
And then shuttering was applied in order to create a concrete replacement to the top half of this wall, which will withstand attack by fast flowing 'torpedo' tree-roots and such much better than the old stone wall would have done.
More shuttering props are added:
 The results were excellent, and the plan is to tie this into the new beam (look back at previous updates from first weeks of the project) on the weir to give greater strength on the corner by the piles blocking the leet in the image below.
Some significant site tidying went on at this point, and we suffered from our first rain delays.  Fortunately this coincided in part with a delay on the arrival of the all-important sluice gates.  In the image below you can see the sluice gates have been installed finally, and the shed has also received its cladding which tones it down a bit.
We have been astonished at the speed that the entire project has been moving along.  I am touching copious quantities of wood as I write this, but hopefully all will run smoothly for the final fortnight.  Boy, will be pleased to see the project completed - not only because we are excited to generate the electricity, but furthermore because we are experiencing some pretty determined river flows just now, and a flood this month really would set things back!

This was the river taken this morning:


Monday, 31 October 2011

Hydro update (about 2 weeks behind where we really are)

After some weeks, I can update you in pictorial form on the progress of the hydroelectric scheme.  Sorry for the delay during the most exciting phase of the project, but I'm afraid we've had quite a busy time of it down at Iford lately.  Nevertheless, here is the update!

Endless shuttering...
 And this was the shuttering mould (upside down, here, and about half built) for the cradle for the screw itself.
 And then, one Monday morning, the procession arrived:

 The screw weighs about 8 tonnes.
 And it somehow had to go in here:
 There was a tree in the way, but this proved no problem for the enormous crane, which simply lifted the steel screw clean over the top of the tree!
 And, at 22 degrees, or thereabouts, the descent into the trough was achieved.


A second update to follow shortly, to bring you up to date with the most recent fortnight, then they were able to put in the gearing system, build a shed to house all the clever control gear, and prepare for the arrival of the great sluice gates and grille for the front.

Saturday, 20 August 2011

Hydro-electric project: weeks 1 & 2

##Note: I had intended to post this on 6 August, when I wrote it, but I pushed the wrong button and it ended up in drafts, so it's 2 weeks out of date.  Another update this weekend, therefore, is on its way for week's 3 and 4.##
One of the most exciting projects in the valley is the construction of a hydro-electric plant in the former eel-trap (below) beside the weir (above).
Once complete, the system should generate enough energy to power between 10 and 15 homes (although the electricity will be sold to the grid initially at least) without impacting the local environment negatively at all.

It has always seemed daft to us that we have this powerful resource running through the valley which is essentially unharnessed.  Indeed, the river at Iford has a long history of providing power in the past: originally Iford Mill had an undershot wheel, and it was in the 1930s or so that this was modified to power an early electricity generator.  This was removed in the 1960s since the valley had been added to the grid (to the great satisfaction of residents who no longer had to contend with brown-outs and having to remove sheep, big-bales, and general river detritus from the grille in front of the generator).  And so, after 50 years or so, the river will be returning to work.

For information on the mills in the area, try this excellent book: Wiltshire and Somerset Woollen Mills, Kenneth Rogers
With permissions received and paperwork signed-off, we have excitedly watched as the civil engineering work has begun.  A benefit of this scheme is that it has provided the perfect opportunity to undertake repairs to the weir and mill leet, and whilst the Dutch firm Spaans-Babcock are manufacturing our 10ft diameter Archimedean screw, the repairs are underway first.
Above, the mill leet before clearing, and below a girder bridge is put in to access the weir with heavy plant.
And here's some of the land-based plant with a gratuitous advert for Suttle's, our contractor.
A collapse some years ago through undercutting has been used to create a fish-ladder as requested by the environment agency, and we are also creating an eel-pass which will assist the passage of elvers upstream; these measures should provide a positive benefit to the natural inhabitants of the river through the diversion of much of the water through the screw.
Below, the fish ladder during construction - it looks a lot better after it's finished apparently.
We'll report as the project takes shape, but having had five power cuts in the last three months, it is an exciting prospect to know that self-sufficiency will be just a cable's-run away in the future should we need to resort to that!
Above, the weir, dried out for inspection, before the major work commenced.